Hello,
I perform the NEGF calculation with 1 core.
the calculation expires more than a week. (0, 0.4, 0.8, 1.2, 1.6 and 2.0 v)
when electricity is cut off, the calculation is not completed.
Finally, the account was left half at 1.6 V.
again, I need to make a calculation from the beginning?
Can I continue the account from 1.6 V value.
Can you help me?
Title: Re: Can I continue the unfinished operation?
Post by: Petr Khomyakov on January 16, 2019, 11:42
You may use the IVCharacteristics study object for being able to do an easy restart, see https://docs.quantumwise.com/tutorials/ivcharacteristics/ivcharacteristics.html and  https://docs.quantumwise.com/webinars/webinars.html#new-framework-for-iv-curve-simulations.